Project update

It is quite amazing to think that over half the year has gone already, and work at Drogo is progressing well. The view from the top of the viewing tower has changed dramatically over the last few months and you can really appreciate what the builders have been up to.

Recently the builders have been;
– Repointing of the south and east wings is well advanced.

001

-Bauder membrane is being laid on the roof starting with vertical sections.

 IMG_4599( view of the roof)

-The East window (the tallest window in the castle) has all the glass back in, we are however waiting for the builders to complete the sealing of these windows.

What’s next?

-Stonework reinstatement will increase during July. This has already started on the east wing.

– More scaffolding is being erected so that the builders can remove the remainder of the parapet.

-The work is continuing to the programme we expect with the south wing being finished for Christmas.

If you would like to know more our project manager leads Hard Hat tours on the building site. Please look at the Castle Drogo website for more details.

 